Main Campus Construction

 

View a live stream of the parking garage construction here.


A rendering of the expanded parking garage

Construction Update March 17 2017

March 17, 2017

Power will be shut off to some buildings on campus Sunday for six hours while crews connect Browning Hall to the main power grid. Also, the garage is nearly complete and the countdown to the grand opening has begun.

tags: webster life, webster today, ISB

A rendering of the interior of Browning Hall

Construction Update Feb 23 2017

February 23, 2017

This week, the two biggest Browning Hall tasks are the installation of the freight elevator, the start of the excavation for storm water pipes, and the removal of excavated earth related to the storm water piping work. The excavation for the storm water piping is expected to last through 2nd next week in March. The freight elevator was delivered earlier this week and the installation is expected to last through the third week of March.

tags: webster life, webster today, ISB